Construction of the $150 million flagship solar energy park in Gonnoruwa, Hambantota District, reached 80% completion entering August 2026 under the Ceylon Electricity Board (CEB) renewable expansion blueprint. The 150-megawatt solar photovoltaic installation incorporates high-efficiency bifacial panels linked via high-voltage underground transmission links to the Hambantota Grid Substation. The facility will generate approximately 240 gigawatt-hours annually, offsetting 180,000 metric tonnes of carbon emissions. Energy ministry engineers confirmed that trial grid synchronization will commence in November, supplying low-cost clean power to Southern Province industrial zones.
MyCountry.News

Published By

MyCountry.News

Colombo

AI Story Intelligence

Need deep context or background on this story?

Ask our AI Analyst for instant verified facts, root causes, historical data, and economic impact.

Ask AI Analyst